Koss Residence
|
April is a big month for framing. The second floor of the main house is getting framed and the concrete beam gets formed and poured.
|
April 1, 2000 View from across Cozy Cove...our house is flanked on the left my Richard McAniff's site (now just lawn and a trailer), and on the right by the Coles' house.
|
|
![]() |
April 3, 2000 Look - it's a crow! |
![]() |
April 3, 2000 The east pool wall. You can see the concrete pillars on which the beam and stairs will rest. |
![]() |
April 7, 2000 Kitchen ceiling joist go up. |
![]() |
April 7, 2000 From the dining room ... a great day to be working outside! |
![]() |
April 7, 2000 We "arborize" some rhododendrons - opening up some views to the lake. |
![]() |
April 7, 2000 Steel moment frame at dining room and master bedroom. |
|
April 7, 2000 Job site as seen from Richard McAniff's property. Richard's kitchen window mock-up is at the right. Click on image below for full size panorama (359K). |
|
![]() |
April 16, 2000 Deb's project room. |
![]() |
April 16, 2000 Kitchen (with dining room behind) as seen from living room. |
![]() |
April 16, 2000 Pool room west wall. |
![]() |
April 16, 2000 Forms and scaffolding for concrete beam. This beam is probably one of the trickiest parts of the concrete work. Both the face and the bottom of the beam have a 210' radius curve; the resulting bottom edge of the beam is the intersection of two 210' cylinders. We're also forming clear plastic strips into the concrete as control joints to minimize any cracking of the concrete over time. We have the option of either leaving the plastic strips in place (and trimming them) or pulling them out completely. |
![]() |
April 18, 2000 We have some flooring on the second floor. Kent and John (architects) are shown here in the master bedroom discussing the upper deck construction. |
![]() |
April 19, 2000 Phil (framer) standing in front of the north living room wall. |
![]() |
April 26, 2000 Paul uses a man-lift to put up the north living room wall. |