Koss Residence
|
Framing and concrete work are completed on the main house. The pool steel is in place and shot-crete is blown in. Next door, Richard McAniff's project gets underway.
![]() |
June 2, 2000 Building a platform over the pool so we don't have to use scaffolding. |
|
June 2, 2000 Good view of the "rain chute" in the front courtyard. |
|
![]() |
June 7, 2000 Our stage is available for square dances, clog dancing, and concerts. Please make arrangements at poolhall@mckoss.com. |
|
June 10, 2000 Project site from the lake. |
|
![]() |
June 13, 2000 The culverts for our kayak storage tubes arrives on site. Getting ready here to poor concrete floors before setting them in place. |
| 3, 2, 1, .....
Blast Off!
|
|
|
June 15, 2000 Design inspiration for our house. I'm going to have to have a little talk with Mr. Fleming to understand what he's trying to imply. We're also going to have to order a water fountain - it looks really natural there.
|
|
![]() |
June 16, 2000 Last night all my keys dropped out of my pack and into the lake ... in 10 feet of murky lake water. But I'm happy to report that I was able to recover them this morning. They look fine - but they smell a little funny. |
|
June 21, 2000 Steel for the pool enclosure begins to go up. |
|