Ground-Breaking Ceremony October 22, 1999 We officially broke ground on our new house construction project.
The architects hosted a ground breaking ceremony at the property that
(foggy) Friday. We hope to move in around We now have a firm move-in scheduled for 5 pm on June 15, 2001. Countdown Timer: ... Visit our Design Web for computerized images of the house design. If you're working on this project (or if you're a friend or family member and would like to notified as I update this site), I'd like to invite you to visit the Koss Residence Community web site. |
| View from Yarrow Point November, 2000
|
|
| September, 2001 | ![]() |
Web Cam out of ServiceWe've gotten far enough along in the project that the web-cams were getting in the way of construction - so we've had to take them down. I plan to update the site with a movie made from all the web cam images. Our friends are building a home in Australia - you can visit their web cam to get your fix of construction web cam viewing. |
|
| November, 1999 | Excavation. |
| December 1999 | Site work. |
| January 2000 | Footings poured, wall layout begins. |
| February 2000 | Concrete walls and slabs poured, guest house framing, steel erection. |
| March 2000 | More concrete and framing. Electrical and plumbing. |
| April 2000 | Framing and concrete beam. |
| May 2000 | Framing and concrete complete! Pool concrete finished. Plumbing and electrical start. Charadrius vociferus nest. |
| June 2000 | HVAC, electrical, kayak storage, key recovery. |
| July 2000 | Pool steel enclosure. |
| August 2000 | Aerial photographs, roofing, duct work, home automation wiring. |
| September 2000 | Lakefront retaining wall, lawn, courtyard wall, pool ceiling steel, pool windows |
| October 2000 | Lakefront patio, entry walkway/arcade, stucco sample, deck waterproofing, fireplace wall, theater framing, leaf art. |
| November 2000 | Courtyard stone and pond, |
| December 2000 | Wallboard, insulation, 2nd-floor bridge and stairs |
| January 2001 | Stucco and siding. |
| February 2001 | Pool roof, hardi-plank and pool finishes. |
| March 2001 | Pool tile and stone, flooring, driveway. |
| April 2001 | |
| May 2001 | |
| June 2001 | Move in! See Completed House Pictures. |
| General Contractor |
![]() |
| Architect | rohleder | borges | fleming |